The University Line Weekly Update

On Monday, November 13, around 4:00 a.m., Pittsburgh Regional Transit contractors will mobilizing at a second work location for construction of the University Line on Sixth Avenue between Grant Street and Ross Street.

Traffic will be reduced to one lane in each direction as shown in the picture below. Bus detours will remain the same. Pedestrian access will be maintained on both sides of the street.

For the first few days, the contractor will be saw-cutting and beginning to perform exploratory excavation.

The construction detour will remain in effect 24/7 until work is finished at this location, which is expected to happen by the end of December.

Construction for the University Line on Fifth Avenue:

Construction activities continue on Fifth Avenue between Market Street and Liberty Avenue adjacent to Triangle ParkThe contractor continues to perform installation of a 12-inch water main and a 15-inch storm drain.

On Monday, November 13, around 6:00 a.m., construction activities will move from the north side adjacent to Triangle Park to the south side adjacent to Market Square as shown in the picture below. 

The travel lane adjacent to Triangle Park will reopen. The center lane and the lane adjacent to Market Square will both be closed. Bus detours will remain the same.

The construction detour will remain in effect 24/7 until work is finished at this location.

While there will be a few weeks when the contractor is moving between work sites on Fifth Avenue and Sixth Avenue, construction activities on Fifth Avenue are expected to be completed by the end of November. 

The contractor will continue to work Monday through Friday from 7 a.m.-5 p.m., weather permitting. The contractor may work on Saturdays if needed to keep the project on schedule.

Thank you for your continued support of this project.

For questions or concerns, please contact brt@rideprt.org or 412-442-2000.

Get updates in your mailbox

By clicking "Subscribe" I confirm I have read and agree to the Privacy Policy.

About PRT Bus Rapid Transit Project Newshub

Pittsburgh Regional Transit, formerly Port Authority of Allegheny County, is the nation’s 26th largest transit agency. Our 2,600 employees operate, maintain, and support bus, rail, and incline service in the Pittsburgh metro area.

Contact