Four New Work Zones Being Added to University Line Construction Next Week
May 23, 2024
.jpg)
Pittsburgh Regional Transit will add four new work locations in downtown Pittsburgh next week.
Last winter, the PRT contractor relocated water and drainage infrastructure at most of the future PRTX station locations. Currently, the contractors are installing foundations and poles for traffic signals and pedestrian lighting. They’re also restoring the roadway, sidewalks, and curbs. Later this summer, bus shelters, accessible ramps, traffic signals and lighting will be installed.
On May 28, PRT’s contractor will establish two additional work sites. The first one is on Sixth Avenue between Smithfield Street and William Penn Place. The second one is on Fifth Avenue between Liberty Avenue and Market Street opposite the current work site.
Traffic on Sixth Avenue between Smithfield Street and William Penn Place will be maintained with one travel lane in each direction (see image above). This single-lane operation will remain in effect 24/7 until late fall.
Mellon Square Garage will be accessible to vehicles and pedestrians. The sidewalk will remain open opposite the work site.

Additionally, construction activities on Fifth Avenue between Liberty Avenue and Market Street will move to the opposite side of the street adjacent to Triangle Park.
To accommodate this new work area, vehicle traffic will be shifted to the opposite side of Fifth Avenue between Liberty Avenue and Market (see image above).
The construction detour will remain in effect 24/7 until work is finished late this fall. The sidewalk will remain open opposite the work site.

On May 31, the contractor will establish two more work sites along Fifth Avenue: one between Smithfield and Grant streets, and the other between Sixth Avenue and Ross Street.
To accommodate the new work area, traffic on Fifth Avenue will be reduced to one travel lane in each direction between Smithfield and Grant streets (see image above). This single-lane operation will remain in effect 24/7 until late fall. The sidewalk will remain open on Fifth Avenue opposite the work site.

Additionally, traffic on Fifth Avenue will be reduced to one travel lane in each direction between Ross Street and Sixth Avenue (see image above). This single-lane operation will remain in effect 24/7 until late fall. The sidewalk will remain open opposite the work site.

Construction to Continue at Sixth Avenue and Diamond Street Next Week
Earlier this week, the PRT contractor established a new work zone on Sixth Avenue between Fifth Avenue and Diamond Street adjacent to the Allegheny County Family Division building.
Work in this area will include installation of foundations for traffic signals and pedestrian lighting followed by replacement of sidewalks and curbs.
To accommodate the new worksite, traffic on Sixth Avenue will be reduced to one travel lane in each direction between Fifth Avenue and Diamond Street. The traffic detour will remain in place 24/7 until late fall.

Construction Activities to Continue at Sixth and Grant Next Week
Last week, the PRT contractor established a new work zone on Sixth Avenue between Grant and Ross Streets.
The electrical subcontractor will be installing conduit for the new bus shelter, pouring a foundation for a new traffic signal, and relocating existing lighting. After the electrical work is complete, the contractor will be replacing the sidewalk, roadway, and granite curbs.
Later this summer, the contractor will install two new 60-foot bus shelters, accessible ramps, and traffic signals.
To accommodate the new work site, traffic on Sixth Avenue will be reduced to one travel lane in each direction between Grant and Ross Streets. The traffic detour will remain in place 24/7 until late fall.

Electrical Work Supporting Traffic Signals to Continue Next Week
The Pittsburgh Regional Transit electrical subcontractor will continue construction activities for traffic signals next week.
Ultimately, 35 new traffic signals will support the University Line bus rapid transit project in downtown Pittsburgh.
Over the next few weeks, the PRT electrical subcontractor will have two crews pouring foundations, installing poles, and running conduit for future traffic signals.
They will be working weekdays from 9:00 a.m. to 3:00 p.m. at the following locations:
- Fifth Avenue and Cherry Way (Old Kauffman’s building garage)
- Fifth Avenue and Sixth Avenue
- Fifth Avenue and Smithfield Street
- Sixth Avenue and Liberty Avenue
- Sixth Avenue and Centre Avenue (8 a.m. to 4:00 p.m.)
- Sixth Avenue and Ross Street
Each location has additional work to be performed. The contractor will move between locations to help keep the project on schedule.
Pedestrian access will always be maintained; however, some of the work may require temporary use of the adjacent parking/travel lane.

Current construction locations for the University Line include:
- Fifth Avenue (between Market Street and Liberty Avenue)
- Sixth Avenue (between Wood Street and Liberty Avenue)
- Sixth Avenue (between Grant Street and Ross Street)
- Sixth Avenue (between Fifth Avenue and Diamond Street)
Thank you for your continued support of this project.
For questions or concerns, please contact brt@rideprt.org or 412-442-2000.